Dear Residents,
The 2020 Paving Project commences in the Farnham area on Wednesday, June 3rd.  Once the Farnham areas are complete, the Paving Project will move to the following areas:  Harwood, Oakridge, Newport, and Prescott. All scheduled work is dependent upon current weather conditions and any potential unforeseen issues.
PAVING:
The asphalt overlay schedule for each Association is as follows:
  • Wednesday, June 3rd:
    >    Farnham A – from the west side of Farnham A parking
    spot # 1012A to the east side of Farnham A parking
    spot # 1037
  •  Thursday, June 4th:
    >    Farnham B – from Farnham A parking spot # 1037 to
    Farham B parking spot # B46
  • Friday, June 5th:
    >    Farnham C/P – from Farnham B parking spot # B46 to
    Farnham C parking spot # C4
    >    Farnham P – north side parking and roadway
All vehicles must be removed from their parking spaces no later than 8:00 AM on the day your Association is scheduled to be paved and cannot be returned to their respective parking spaces until the following morning.  If your vehicle is in a parking space when the paving begins, it is likely to be towed by your Association at your own expense.
While paving is being done, one lane of the roadway will remain open at all times to allow for local traffic.  The roadway will be fully reopened upon completion of paving that same day.
PARKING WILL BE AVAILABLE AT THE CLUBHOUSE, IF NEEDED
(FIRST LOT TO THE RIGHT AS YOU ENTER OFF OF CENTURY BOULEVARD). VEHICLES ARE ONLY ALLOWED TO PARK AT THE CLUBHOUSE ON THE DAY/DATE YOUR ASSOCIATION IS SCHEDULED TO BE PAVED OR MILLED.  YOU MUST OBTAIN A PASS FROM THE BAY MANAGEMENT STAFF OFFICE LOCATED AT THE CLUBHOUSE. The pass will be date stamped and should be placed on the dashboard of your vehicle to avoid being towed at your own expense.
Residents planning to be away during this time and leaving a vehicle at the Association should make arrangements to leave keys with a resident who resides on the property full time so their vehicle can be moved during the paving process.   Please advise Ray DePerro of Five Star Sealing and Paving during normal business hours of 9:00 AM to 5:00 PM at (954) 650-2347 the name, unit number, and telephone number of the individual that will have your keys.  Again, if your vehicle is in a parking space when the paving begins, it is likely to be towed by your Association at your own expense.
 
(Note: Tack is used in the paving process and is a liquid asphalt product that increases the cohesion of the asphalt.  Please do not drive or walk on marked areas where tack has been applied, as this product is difficult to remove.  If you inadvertently get tack on your car, “Go-Jo” or an orange oil-based product such as “Citri-Solv” has proven beneficial in removing tack from automobiles, shoes, etc.)
Please read important information that is posted at your respective buildings.
 
Additional information and scheduling notices for the Farnham area will be posted one week prior to the Associations being paved.  Please watch for additional updates on the continuation of the 2020 Paving Project at:
 
Remaining Associations that are part of the 2020 Paving Project will be notified in advance of the dates they are scheduled to be done.
Should you have any questions regarding the paving process, please contact Robert Streather, CVE Master Management, at (954) 913-9142 or Ray DePerro of Five Star at (954) 650-2347 during normal business hours of 9:00 AM to 5:00 PM.
 
Thank you,
Vallen A. Smikle
Executive Director