IMPORTANT PAVING UPDATE:

Paving will temporarily suspend during the Jewish Holy Days as our paving contractor takes their annual vacation during that time.

Please see the revised schedule for next week, September 14th. Paving will resume on Tuesday, September 29th, following Yom Kippur.
PAVING:
The asphalt overlay schedule is as follows:

  • Monday, September 14th: Newport G
    Roadway and parking spaces from the south end of the building to the center of the building
  • Tuesday, September 15th: Newport G
    Roadway and parking spaces from the center of the building to the north end of the building
  • Wednesday, September 16th: PAVING SUSPENDED UNTIL TUESDAY, SEPTEMBER 29TH
  • Tuesday, September 29th: Newport A
    Roadway and parking spaces from Newport Drive heading east to the curve
  • Wednesday, September 30th: Newport K
    Roadway and parking spaces along Newport Drive, east side of the street (one lane only), from the south end of Newport K to the intersection of Prescott B & E. (This includes any parking spaces along Newport Drive which affect buildings C, D, E, F, & J.)
  • Thursday, October 1st: Prescott E & Newport Drive
    Newport Drive roadway along with Prescott E roadway and parking spaces. One lane only, from the intersection at Newport K heading north and then west onto Prescott Place to the end of Prescott E.
  • Friday, October 2nd: Prescott C & D
    Roadway and parking spaces

All vehicles must be removed from their parking spaces no later than 8:00 AM on the day your Association is scheduled to be paved and cannot be returned to their respective parking spaces until the following morning. If your vehicle is in a parking space when the paving begins, it is likely to be towed by your Association at your own expense.

While paving is being done, one lane of the roadway will remain open at all times to allow for local traffic. The roadway will be fully reopened upon completion of paving that same day. Residents may experience some detours in the affected areas, as well as limited access during paving.

PARKING WILL BE AVAILABLE AT THE CLUBHOUSE, IF NEEDED (FIRST LOT TO THE RIGHT AS YOU ENTER OFF OF CENTURY BOULEVARD). VEHICLES ARE ONLY ALLOWED TO PARK AT THE CLUBHOUSE ON THE DAY/DATE YOUR ASSOCIATION IS SCHEDULED TO BE PAVED. YOU MUST OBTAIN A PASS FROM THE CENCLUB STAFF OFFICE LOCATED AT THE CLUBHOUSE. The pass will be date stamped and should be placed on the dashboard of your vehicle to avoid being towed at your own expense.

Residents planning to be away during this time and leaving a vehicle at the Association should make arrangements to leave keys with a resident who resides on the property full time so their vehicle can be moved during the paving process. Please advise Ray DePerro of Five Star Sealing and Paving during normal business hours of 9:00 AM to 5:00 PM at (954) 650-2347 the name, unit number, and telephone number of the individual that will have your keys. Again, if your vehicle is in a parking space when the paving begins, it is likely to be towed by your Association at your own expense.

(Note: Tack is used in the paving process and is a liquid asphalt product that increases the cohesion of the asphalt. Please do not drive or walk on marked areas where tack has been applied, as this product is difficult to remove. If you inadvertently get tack on your car, “Go-Jo” or an orange oil-based product such as “Citri-Solv” has proven beneficial in removing tack from automobiles, shoes, etc.)

Please read important information that is posted at your respective buildings.

Please watch for additional updates on the continuation of the 2020 Paving Project at:
www.KeepingCVEBeautiful.com

Remaining Associations that are part of the 2020 Paving Project will be notified in advance of the dates they are scheduled to be done.

Should you have any questions regarding the paving process, please contact Robert Streather, Director of Operations for CVE Master Management, at (954) 913-9142 or Ray DePerro of Five Star Paving at (954) 650-2347 during normal business hours of 9:00 AM to 5:00 PM.