URGENT PAVING SCHEDULE UPDATES BELOW:

There are important changes to the recent paving schedule for the Berkshire area.

MILLING FOR BERKSHIRE E & A HAS BEEN POSTPONED.

Milling for Berkshire E will commence on Friday, July 30th.

Paving for Berkshire C will commence tomorrow, July 22nd. (All scheduled work is dependent upon current weather conditions and any potential unforeseen issues.)

PAVING:
The NEW asphalt overlay schedule for July 22nd through August 6th is as follows:

  • Thursday, July 22nd: Berkshire C
    Berkshire C roadway and parking spaces, entrance lane from Century Boulevard and the right side of the building. Also, secondary parking lot (Guest Parking).
  • Friday, July 23rd: Berkshire C
    Berkshire C roadway and parking spaces, exit lane to Century Boulevard and the left side of the building.
  • Monday, July 26th: Berkshire B
    Berkshire B roadway and parking spaces from the entrance roadway to the east end of the building.
  • Tuesday, July 27th: Berkshire B
    Berkshire B roadway and parking spaces from the entrance roadway to the west end of the building.
  • Wednesday, July 28th: Berkshire D
    Berkshire D roadway and parking spaces from the west end of the building to the center of the building.
  • Thursday, July 29th: Berkshire D
    Berkshire D roadway and parking spaces from the center of the building to the east end of the building.
  • Friday, July 30th: Berkshire E (MILLING ONLY)
    Berkshire E roadway and parking spaces (MILLING ONLY).
  • Monday, August 2nd: Berkshire E (PAVING)
    Berkshire E roadway and parking spaces from the west end of the building to the center of the building.
  • Tuesday August 3rd: Berkshire E (PAVING)
    Berkshire E roadway and parking spaces from the center of the building to the east end of the building.
  • Wednesday, August 4th: Berkshire A (MILLING ONLY)
    Berkshire A roadway and parking spaces (MILLING ONLY).
  • Thursday, August 5th: Berkshire A (PAVING)
    Berkshire A roadway and parking spaces from the north end of the building to the fourth tower (approximately two thirds of the building).
  • Friday, August 6th: Berkshire A (PAVING)
    Berkshire A roadway and parking spaces from the fourth tower to the south end of the building, including guest parking lot.

This will complete the Berkshire area and the Paving Project will continue into the Keswick area with detailed scheduling to be announced. (All scheduled work is dependent upon current weather conditions and any potential unforeseen issues.)

All vehicles must be removed from their parking spaces no later than 8:00 AM on the day your Association is scheduled to be paved or milled. If your area is being paved, you cannot return your vehicle to the newly paved area until the following day. If your area is being milled, you may return your vehicle to your assigned parking space after milling is complete the same day. If your vehicle is in a parking space when the paving or milling begins, it is likely to be towed by your Association at your own expense.

While paving or milling is being done, one lane of the roadway will remain open at all times to allow for emergency vehicles and/or local traffic. The roadway will be fully reopened upon completion of paving or milling that same day. Residents may experience some detours in the affected areas, as well as limited access during paving and milling.

PARKING WILL BE AVAILABLE AT THE CLUBHOUSE, IF NEEDED (FIRST LOT TO THE RIGHT AS YOU ENTER OFF OF CENTURY BOULEVARD). VEHICLES ARE ONLY ALLOWED TO PARK AT THE CLUBHOUSE ON THE DAY/DATE YOUR ASSOCIATION IS SCHEDULED TO BE PAVED. YOU MUST OBTAIN A PASS FROM THE CENCLUB STAFF OFFICE LOCATED AT THE CLUBHOUSE. The pass will be date stamped and should be placed on the dashboard of your vehicle to avoid being towed at your own expense. NOTE: WHEN THE MILLING ONLY IS BEING DONE, YOU CAN RETURN YOUR VEHICLE TO YOUR PARKING SPACE THE SAME DAY.

Residents planning to be away during this time and leaving a vehicle at the Association should make arrangements to leave keys with a resident who resides on the property full time so their vehicle can be moved during the paving process. Please advise Ray DePerro of Five Star Sealing and Paving during normal business hours of 8:00 AM to 4:00 PM at (954) 650-2347 the name, unit number, and telephone number of the individual that will have your keys. Again, if your vehicle is in a parking space when the milling or paving begins, it is likely to be towed by your Association at your own expense.

(Note: Tack is used in the paving process and is a liquid asphalt product that increases the cohesion of the asphalt. Please do not drive or walk on marked areas where tack has been applied, as this product is difficult to remove. If you inadvertently get tack on your car, “Go-Jo” or an orange oil-based product such as “Citri-Solv” has proven beneficial in removing tack from automobiles, shoes, etc.)

Please read important information that is posted at your respective buildings.

Additional information and scheduling notices for paving of the Keswick and Islewood areas will be posted in advance. Please watch for additional updates on the continuation of the 2021 Paving Project at:
www.KeepingCVEBeautiful.com

Remaining Associations that are part of the 2021 Paving Project will be notified in advance of the dates they are scheduled to be paved.

Should you have any questions regarding the paving process, please contact Robert Streather, Director of Operations for CVE Master Management, at (954) 913-9142 or Ray DePerro of Five Star Paving at (954) 650-2347 during normal business hours of 8:00 AM to 4:00 PM.